TfL Construction Logistics Plan Guidance: What Your CLP Needs to Include

Updated: 2 minutes ago
If you're developing in London, the council will almost certainly ask for a Construction Logistics Plan (CLP), and it will expect it to follow Transport for London's Construction Logistics Planning guidance. This guide explains what that guidance requires: which schemes need a CLP, the difference between Outline and Detailed CLPs, the sections a CLP must include and the measures councils expect to see.
For practical advice on running a site day to day, see our companion guide: Construction Site Logistics Plan: Balancing Build and Safety on Live Sites.
What is the TfL CLP guidance?
TfL's Construction Logistics Planning Guidance (version 1.2, April 2021) was developed by Transport for London and adapted by CLOCS (Construction Logistics and Community Safety) for use across the UK. Most London boroughs expect CLPs to follow it, and it sits behind London Plan Policy T7, which covers deliveries, servicing and construction.
Its aim is to make sure construction traffic is planned from the start, so that a scheme's impact on road safety, congestion, the environment and the local community is kept as low as possible.
Does your scheme need a CLP? The impact levels
The guidance sorts developments into three levels:
Impact level | Typical scheme | What's needed |
Lower | Construction cost under £2m, and smaller than the thresholds below | Construction details go in the Transport Assessment; a Detailed CLP may still be asked for if there are specific issues |
Medium | Over £2m, or 10 or more homes, or 1,000m² or more of floorspace created or changed | Outline CLP and Detailed CLP |
Higher | Over £23m, or 100 or more homes, or 10,000m² or more of floorspace | Outline CLP and Detailed CLP, with specialist input |
Local circumstances can move a scheme up or down a level. A small site on a narrow street, next to a school or on a bus route can be treated as higher impact than its size suggests. Councils can ask for a CLP on any scheme where they're concerned about construction impacts.
Outline CLP vs Detailed CLP
Outline CLP
Prepared at planning stage and submitted with the planning application
Written by planning specialists, such as a transport consultant, working with the developer
Sets out the commitments the construction must meet
Committed measures are usually secured through the Section 106 agreement or planning conditions
Detailed CLP
Prepared before construction starts, usually to discharge a planning condition
Written by the contractor, building on the Outline CLP
Updated throughout construction
The council approves both and enforces them. The developer remains responsible for making sure the commitments are delivered.
What a CLP must include
The guidance sets out a standard structure:
Introduction: the site, the development and who is responsible for the CLP
Context, considerations and challenges: local roads, schools, bus routes, cycle lanes, neighbours and any other sensitivities
Construction programme and methodology: the phases of work and what happens in each
Vehicle routing and site access: routes to and from the strategic road network, site access points, loading and holding areas, usually backed by swept path analysis
Strategies to reduce impacts: the planned measures (see below)
Estimated vehicle movements: how many vehicles, of what type, in each phase
Implementing, monitoring and updating: how the plan will be checked and kept up to date
Planned measures
The heart of a CLP is its list of planned measures. The guidance classes each one as Committed (secured and required), Proposed (feasible, but needing further study) or Considered (relevant at a later stage). Typical measures include:
Vehicle safety and environmental standards, such as CLOCS, FORS and the Direct Vision Standard
Designated routes and agreed delivery times
Out-of-peak or out-of-hours deliveries, avoiding school run times and busy periods
Holding and call-off areas, so lorries don't queue or circulate near the site
Consolidation centres, to reduce the number of deliveries
Freight by water or rail where it's practical
Off-site manufacture and re-use of materials on site
Collaboration with nearby sites and a staff travel plan
Measures need to be specific and measurable, so the council can check they're being delivered.
Vehicle safety in London: CLOCS, FORS and the Direct Vision Standard
London CLPs are expected to commit to recognised safety standards:
CLOCS is the industry standard for managing construction vehicle safety, covering vehicles, drivers and site arrangements.
FORS (Fleet Operator Recognition Scheme) accredits fleet operators. The CLOCS Standard requires operators to meet the FORS Silver requirements.
The Direct Vision Standard (DVS) applies to all HGVs over 12 tonnes in Greater London. Since 28 October 2024, they need at least a three-star rating, or the Progressive Safe System fitted, to get an HGV Safety Permit.
A CLP that ignores these is unlikely to be approved.
Monitoring
The guidance expects CLPs to be monitored and updated, not filed and forgotten. Typical monitoring covers:
vehicle numbers by type and size, and delivery times against the schedule
breaches of routes or times, queuing or illegal parking, and complaints from neighbours
compliance with vehicle standards, LEZ and ULEZ, and anti-idling
safety incidents involving construction vehicles
named people responsible for the CLP, with the CLP reviewed before each new phase
Who should write a CLP?
CLOCS runs a CLP Practitioner accreditation (Foundation, Practitioner and Advanced levels), and some boroughs recommend that anyone writing a CLP holds it. Whoever prepares it, the Outline CLP needs to be realistic. Commitments made at planning stage become the contractor's obligations later.
Real example: residential development in Newham
A client faced possible refusal because of concerns about construction impacts on a busy high street. Site access was limited, with TfL bus routes and heavy footfall right outside.
Our solution:
agreed delivery windows outside peak hours
proposed a gantry so pedestrians could keep moving along the high street
designed dedicated pedestrian protection measures
used swept path analysis to show vehicles could use the proposed loading area safely
Result: planning approved, with highways officers describing the logistics planning as "exemplary".
How CLPs fit with other documents
A CLP rarely stands alone. It usually sits alongside:
a Delivery and Servicing Plan for once the building is occupied
swept path analysis for site access and loading
parking stress surveys where workers' parking is a concern
Common reasons CLPs are sent back
Generic templates that don't reflect the actual site
No swept path analysis for the largest vehicles
Unrealistic commitments, such as delivery times the contractor can't keep
Missing safety standards: no commitment to CLOCS, FORS or the Direct Vision Standard
No monitoring, or no named person responsible
Ignoring local sensitivities, such as schools, markets, bus stops and cycle lanes
How Capital Transport Planning can help
We prepare Outline and Detailed Construction Logistics Plans across London, following TfL's guidance and each borough's own requirements. Our Principal Consultant, Michael, personally oversees every CLP.
Free initial consultation: we'll tell you what your scheme needs
48-hour quotes
14-day turnaround when deadlines are tight
Direct access to our Principal Consultant
See our Construction Logistics Plan services.
Need a CLP for your development? Get in touch for a free consultation.
Frequently asked questions
When is a Construction Logistics Plan required in London? Under TfL's guidance, schemes of 10 or more homes, 1,000m² or more of floorspace, or a construction cost over £2m need an Outline CLP and a Detailed CLP. Councils can also ask for one on smaller schemes where construction could cause problems.
What is the difference between an Outline and a Detailed CLP? An Outline CLP is submitted with the planning application and sets out the commitments. A Detailed CLP is prepared by the contractor before construction starts, usually to discharge a planning condition, and is updated during the build.
Who approves a CLP? The local planning authority approves and enforces it. TfL may be consulted, particularly where a site is on or near the TfL Road Network.
What is CLOCS? CLOCS (Construction Logistics and Community Safety) is the industry standard for managing construction vehicle safety. Most London CLPs commit to it.
Do construction lorries need a Direct Vision Standard permit? Yes. HGVs over 12 tonnes need an HGV Safety Permit to operate in Greater London, which since October 2024 means at least a three-star DVS rating or the Progressive Safe System fitted.