S38 vs S278 Agreements: What's the Difference?

Writer: Michael Okubajo
Michael Okubajo
2d
6 min read

The short answer: a Section 278 agreement lets you carry out works on a road that is already public highway. A Section 38 agreement is how a new road you build becomes public highway, adopted and maintained by the council.

Both come from the Highways Act 1980, and both are agreements between a developer and the local highway authority. They are easy to confuse because they share the same paperwork: technical approval, a bond, inspection fees and often a commuted sum. But they answer different questions. S278 asks can you change the existing road? S38 asks will the council take on your new one?

If your planning permission includes a new site access, junction changes or footway works, you will almost certainly need one of them, and sometimes both. This guide explains the difference, when each applies and what to expect from the process.

What is a Section 278 agreement?

A Section 278 agreement lets a developer carry out works on the existing public highway, at the developer's own expense, to standards the council approves. Nothing can be built until the council has given technical approval to the design.

Typical S278 works include:

  • a new or widened site access or vehicle crossover onto a public road

  • junction changes, such as new turning lanes, signals or a mini-roundabout

  • new or relocated pedestrian crossings and dropped kerbs

  • footway widening, resurfacing or public realm improvements around the site

  • changes to parking bays, loading bays and road markings, often with a Traffic Management Order

The road stays public highway throughout. You are paying to change it, so the council needs to be satisfied the design is safe and will last.

What is a Section 38 agreement?

A Section 38 agreement is how a new road built as part of a development becomes public highway. The developer builds it to the council's standards, and once it passes inspection the council adopts it and maintains it at public expense from then on. Doncaster Council sums it up as the legal means by which a new estate road becomes a public highway.

S38 is most common on larger residential schemes with new estate roads, but it also applies to new roads serving commercial or industrial sites. Without it, a new road stays private, and the developer, a management company or the residents are responsible for its upkeep indefinitely.

There is an alternative, Section 37, where a developer finishes the road and then gives notice to dedicate it. It is generally seen as a less certain route than a Section 38 agreement, so most developers and councils prefer S38.

S38 vs S278 at a glance


Section 278

Section 38

Works on

Existing public highway

New road built by the developer

End result

The public road is altered or improved

The new road becomes public highway

Typical examples

Site access, junction changes, crossings, footway works

New estate roads, footways and lighting within a development

Who builds it

Developer, to the council's approved design

Developer, to the council's adoption standards

Bond or cash security

Yes, usually covering the full cost of the works

Yes, usually covering the full cost of the works

Inspection and approval fees

Yes, set by each council

Yes, set by each council

Commuted sum for future maintenance

Possible, usually paid before works start

Possible, usually paid before adoption

Who maintains it afterwards

The council, as before, once the works are signed off

The council, once the road is adopted

Bond, fee and commuted sum rules vary between councils, so always check your highway authority's own guidance. The ADEPT guidance on commuted sums sets out the common approach.

When you need both

Many schemes need a Section 278 and a Section 38 agreement at the same time. A typical case is a housing development with a new internal estate road (S38) that joins an existing public road through a new junction (S278).

Some councils handle this with a combined S38/278 agreement, so the bond, inspections and sign-off run together. Others keep two separate agreements. Where the line between them falls, at the kerb line, the junction mouth or the site boundary, is agreed with the council at technical approval stage, so it is worth settling early.

In London, where most developments sit on existing streets, S278 is far more common than S38. Many London schemes only need an S278 agreement for access, footway and parking changes.

The process: approval, bonds, fees and timescales

The steps are broadly the same for both agreements, though every council runs its own version. A typical process looks like this:

  1. Submit the design package. This includes layout and level plans, drainage, lighting, signs and lines, materials, and a Stage 1 Road Safety Audit.

  2. Technical review. The council checks the design and may ask for changes. Review periods vary between councils, but four to six weeks is common, and officer time is often charged in advance.

  3. Stage 2 Road Safety Audit. This is completed on the detailed design before technical approval.

  4. Technical approval. The council confirms the approved plans and sets the bond, the inspection fee (often a percentage of the works cost) and any commuted sums.

  5. Legal agreement. The council's solicitor drafts the agreement, with legal costs charged separately.

  6. Pay, secure the bond, then build. The bond, fees and commuted sums are settled before work starts, and the council inspects the works as they progress.

  7. Stage 3 Road Safety Audit and completion. After the works, a maintenance period follows, often 12 months, before the final certificate is issued and the bond released.

Plan for time. From first submission to starting on site, several months is normal, especially when legal drafting and Traffic Management Orders are involved. Starting the process as soon as planning permission is granted, or before, avoids holding up construction.

Common pitfalls

  • Starting too late. Treating the highway agreement as a post-planning formality is the most common cause of delays to site start.

  • Designs that don't meet the council's standards. Each authority has its own materials, kerb and lighting specifications. A design that ignores them goes round the review loop again.

  • Unclear boundaries. If the split between S38 and S278 areas, or between highway and private land, isn't agreed early, plans and the legal agreement have to be redrawn.

  • Forgetting the costs beyond construction. The bond, inspection fees, legal fees, commuted sums and any Traffic Management Order all need budgeting from the start.

  • Skipping road safety audits. Missing or late Stage 1 and 2 audits hold up technical approval.

  • Starting work on the highway before the agreement is signed. Councils will not let works on the public highway begin until the agreement and bond are in place.

How Capital Transport Planning can help

We support developers, architects and contractors through Section 278 and Section 38 agreements across London and the South East, from the first highway design to final sign-off. With six years' experience working at Hammersmith & Fulham Council, we know what highway authorities look for and how to keep approvals moving.

  • highway design for site access, junctions and footway works

  • technical approval submissions and liaison with the council

  • coordinating road safety audits, bonds and cost estimates

  • support through construction, inspections and final certification

Need an S278 or S38 agreement for your scheme? Get in touch for a quote.

Frequently asked questions

What is the difference between S38 and S278 agreements? A Section 278 agreement covers works to an existing public road, such as a new access or junction. A Section 38 agreement covers a new road built by a developer that the council will adopt as public highway.

Do I need a Section 278 agreement for a new site access? Usually, yes. Any new or altered access onto a public road counts as work on the existing highway. Small vehicle crossovers are sometimes handled under a simpler licence instead, depending on the council.

Can S38 and S278 be combined? Yes. Many councils use a combined S38/278 agreement when a new estate road connects to an existing road, so the bond and inspections run together.

Who pays for S278 and S38 works? The developer pays for the design, construction, council fees and legal costs, and provides a bond. A commuted sum for future maintenance may also be required.

How long does a Section 278 agreement take? Technical review alone often takes four to six weeks, and the whole process from submission to starting on site commonly takes several months. Starting early is the best way to avoid delays.

What is a commuted sum? A one-off payment to the highway authority towards the future maintenance of new or improved highway features, such as non-standard materials, trees or extra lighting.

Sources

 
 
 

Recent Posts

See All

Comments


Capital Transport Planning logo

​Capital Transport Planning is an independent consultancy delivering expert transport planning and infrastructure solutions across the UK.

  • Facebook
  • Youtube
  • Instagram
  • LinkedIn

Richmond Office,
Greater London

Address: Parkshot House, 5 Kew Road Richmond upon Thames, TW9 2PR

E: info@capitaltp.co.uk
P: +44 (0)208 1681 911

© 2026 by CTP. All rights reserved.

Website Made By DesignByComfy

bottom of page