CMP vs CLP vs CTMP: What's the Difference?

Councils use three similar names for construction-stage transport documents, and the names are often mixed up. They overlap a lot, but each has a different focus and is asked for at a different point in the planning process. Which one you need depends on the council and the size of the site.
Document | Main focus | Usually asked for | Common in |
Construction Logistics Plan (CLP) | Vehicle movements to and from site: numbers, routes, timing, vehicle safety standards and ways to cut trips | Outline CLP with the planning application; detailed CLP before work starts | London boroughs and TfL, following TfL/CLOCS guidance |
Construction Management Plan (CMP) | The whole construction impact: logistics plus noise, dust, working hours, site layout and neighbour liaison | Usually by planning condition or S106, before work starts | Many London boroughs, often using the council's own pro-forma |
Construction Traffic Management Plan (CTMP) | Managing construction traffic on the road network: access, routing, banksmen, traffic management, parking suspensions | By planning condition before work starts | Councils outside London and larger schemes |
Construction Logistics Plan (CLP)
The CLP comes from Transport for London's construction logistics guidance, written with CLOCS (Construction Logistics and Community Safety). It focuses on the supply chain: how many vehicles will come to site, which routes they will use, when deliveries happen, and how to reduce trips through measures like consolidation or delivery booking. TfL guidance notes that a CLP is developed earlier in planning than a CMP and focuses only on logistics.
An outline CLP supports the planning application. A detailed CLP follows once a contractor is appointed and the methods are known. For more detail, read our guide to TfL Construction Logistics Plan guidance.
Construction Management Plan (CMP)
A CMP covers more ground. As well as logistics, it deals with how the site is run: hoardings, working hours, noise and dust, community liaison and how complaints are handled. Some boroughs ask for the CMP on their own pro-forma, which must be completed and signed.
Construction Traffic Management Plan (CTMP)
A CTMP concentrates on traffic on the highway: the access point, turning, gate management, wheel washing, temporary traffic management and any parking bay suspensions or road closures. It is the most common name outside London.
Which one do you need?
Read the planning condition or the pre-application advice. It names the document and often the template to use. If more than one is asked for, a single combined document is often accepted, as long as it covers every heading in each.
How Capital Transport Planning can help
Capital Transport Planning prepares CLPs, CMPs and CTMPs for sites of all sizes, including outline documents for planning and detailed plans to discharge conditions. Call us on 020 8168 1911.
See our Construction Logistics Plan services and swept path analysis, or get in touch for a quote.
About the author: written by Michael Okubajo, Director of Capital Transport Planning, a Chartered Town Planner (MRTPI) and member of the Chartered Institution of Highways & Transportation (CIHT), with a postgraduate degree in Transport and City Planning from University College London (UCL).



Comments